Work Plan 2008 Work Plan 2008

Date added: 03/13/2014
Date modified: 04/09/2014
Filesize: 1.14 MB
Downloads: 55

Community Awareness activities: 614 village on UXO risk education activities. 101% of the work plan target completed.
General Survey tasks: 2,200 survey tasks in 1,422 villages. 121% of the work plan target completed.
Roving tasks: 1,672 roving tasks in 1,151 villages. 113% of the work plan target completed.
Area clearance operations: 2,608.9 hectares of land cleared. 103% of the work plan target completed.
Technical Survey tasks: re-classified 589.5 hectares of land cleared. 106% of the work plan target completed.
Support to development agencies: 167 hectares of land for more than twenty different development agencies